Place St Maur des Fosses

Project Overview

PVR Contracting Ltd helped transform Place St Maur des Fossés from a rundown central area into a vibrant and accessible public space, forming the first stage of the wider Bognor Regis regeneration programme. 

Delivered for Ground Control Ltd and Arun District Council, the £1.3 million Levelling Up Fund project created a distinctive new public realm incorporating interactive fountains, water play, high-quality paving, sustainable drainage, raised planters and infrastructure for community events. 

The works were delivered under a JCT Intermediate Building Contract with Contractor’s Design. LUC, represented by Alex Massey, provided the landscape architecture input. 

Construction commenced in January 2022. Substantial completion was achieved in July 2022, allowing the new public space to open for the summer holidays, with the remaining finishes completed in September 2022. 

Scope of Works

  • Construction of an interactive fountain and water play area 

  • Installation of underground tanks to collect, manage and reuse water 

  • Construction of a dedicated water-management and drainage system 

  • Installation of patterned paving designed to replicate the appearance of a beach 

  • Use of specific impervious paving to direct water into the collection and reuse system 

  • Installation of slot drainage to protect the water play area from surrounding surface water 

  • Creation of sustainable drainage system planters 

  • Construction of raised brick planters 

  • Installation of pop-up power supplies to support fairs, markets and community events 

  • Laying paving using Instarmac bedding and jointing materials 

  • Construction of an above-ground pump chamber enclosure using stone-filled gabions and a green roof

 

Highlights & Key Benefits

  • Transformed a rundown town-centre area into a vibrant, accessible public space 

  • Reduced the tender value from £1.6 million to the available £1.3 million budget through value engineering 

  • Created a water-efficient play space using underground collection, drainage and reuse systems 

  • Provided flexible infrastructure for fairs, markets and community events 

 

Project Delivery Challenges & Solutions

  • Fixed summer opening: Changed unavailable coloured macadam to resin-bonded surfacing over macadam, allowing the space to open in July 2022 

  • Underground constraints: Managed multiple buried services and former structures through investigation and CBR testing 

  • Imported paving: Carefully coordinated the single available delivery from the Netherlands to protect the programme 

  • Public access: Sequenced the works to maintain north-to-south pedestrian access throughout construction 

 

Community Engagement

  • Maintained north-to-south public access throughout the works to minimise disruption 

  • Achieved substantial completion in time for residents and visitors to use the space during the summer holidays 

  • Installed pop-up power supplies to support future fairs, markets and community activities 

 