Headstone Manor Park
Project Overview
A major SuDS and flood alleviation scheme within a nationally significant heritage park. Works included de-culverting watercourses, creating new wetlands and improving access while protecting heritage assets and maintaining public use.
-
Ground Control Ltd for London Borough of Harrow
-
Principal Subcontractor – Earthworks, NFM, Hard & Soft Landscaping
-
Flood Alleviation / Heritage Parks
-
£2.8m (PVR Delivery: £1.5m)
-
April 2019 – March 2021
-
23-hectare heritage park
-
Headstone Manor Park, Harrow
-
Scheduled Monument · Listed structures · Heritage Lottery Funded
Scope of Works
SuDS ponds, wetlands, reed beds and sediment ponds
De-culverting sections of Yeading Brook
2.5 km of new and upgraded paths; seven bridges
Overflow car park, play area and soft landscaping
Highlights & Key Benefits
National award-winning scheme
Major flood alleviation and ecological enhancement
Improved visitor access and heritage experience
Project Delivery Challenges & Solutions
Asbestos-impacted soil resolved via revised MMP and landform redesign
Seasonal programming to avoid ecological constraints
COVID shutdown managed with revised RAMS
Community Engagement
Weekly client and stakeholder meetings
Public access maintained throughout via phased works
Engagement with museum, nursery and residents